Cardinal Glennon Hospital

Four-Story Concrete Hospital Addition

St Louis, MO

  • Cardinal Glennon Hospital Addition, St. Louis MO
  • Cardinal Glennon Hospital Addition, St. Louis MO

Cardinal Glennon Hospital

South Central Operation

This four-story concrete hospital addition was built in St. Louis, MO by Ceco Concrete Construction, LLC – a nationwide design-assist structural concrete contractor.┬áCeco worked successfully between two fully-operational hospital buildings, working to reduce impact on patients, staff and visitors throughout construction. First level framing was performed over active steam and electrical lines that could not be shut-down during construction. The site had very limited storage space and material deliveries were restricted to reduce impact on hospital operations.

Project Details

  • Project Owner:
    SSM Healthcare
  • Contractor:
    Alberici Construction
  • Architect:
    Christner
  • Structural Engineer:
    SSE
  • Gross Building Area:
    121,125
  • CECO Scope:
    Concrete Formwork
  • Gross Budget:
    1,200,000
  • Date Completed:
    2006